Extension 220 kV field in Lixhe (Liège) with a field which is connected to a new - to be provided - 220 kV/15kV transformer.
Client: Elia Engineering
Location: Lixhe (Liège)
Period: february 2012 - june 2014, engineering: 8 months, construction: 20 months
Engineering hours: 4,000
Construction hours: 4,000